Project / Customer
Project: An effective solution for boiler draft fans: development, manufacturing and supply of high-voltage electric motors of the proprietary "EF" brand for new CHP units.
Customer: A major Russian power generation company
Equipment: Boiler draft fan systems (induced draft fans and forced draft fans)
Product: Asynchronous high-voltage electric motors of the proprietary "EF" brand
Manufacturing geography: PRC (own certified production site)
Introduction
As part of the construction of new CHP units, the customer needed to select electric motors for boiler draft fans of types VDN-31.5K-0.95, DN-32x2-0.62K-0.97 and DRG-32-100.
The engineers of "Energofront" faced a complex task: to develop and supply a batch of asynchronous electric motors with a capacity of 1250 kW, 2000 kW and 1600 kW within a tight schedule, ensuring their reliable direct-on-line starting and operation in extreme climatic conditions.
Key challenges at the start:
Task and technical requirements
To develop, manufacture and supply a batch of asynchronous electric motors with the following parameters:
|
Item |
Machine type |
Required power, kW |
Speed, rpm |
Special conditions |
|
1 |
VDN-31.5K-0.95 |
1250 |
750 |
Operation in a mode with high overload capacity |
|
2 |
DN-32x2-0.62K-0.97 |
2000 |
600 |
Operation in a mode with high overload capacity |
|
3 |
DRG-32-100 |
1600 |
750 |
Increased starting torque |
Key engineering task: to calculate and design electric motors with specified starting characteristics, taking into account direct-on-line starting and operation in low ambient temperature conditions, ensuring the start-up of draft fans within the required time to avoid overheating.
Individual engineering solutions
1. Aerodynamic analysis
The "Energofront" engineers requested the characteristics of the draft fans and performed a recalculation of the reduced aerodynamic curves (dependence of the mechanism resistance on performance). Based on this data, the motor characteristics (electromagnetic torque shape) were adjusted, which made it possible to eliminate "dips" when reaching the operating mode.
2. Engineering and design adaptation
Motors were designed with the following technical features:
Accounting for the moments of inertia of the mechanism rotor:
3. Production at the site in the PRC
Production was deployed at a certified site in China. Why this became an advantage:
Testing and quality control
All electric motors passed the full cycle of factory tests according to the GOST methodology (IEC analogue):
Test results: Actual deviations in no-load current and efficiency did not exceed the passport values (+0.5%). The motors successfully operated for 2 hours in a forced mode (10% overload). Locked rotor tests: 5.54 In, 1.62 Tn.
Implementation at the customer's site
The supply of electric motors with a complete set of accompanying documentation (Drawings, operation manual, Passports, test protocols, quality certificates, installation instructions) was completed within the strictly agreed timeframe.
Summary of achieved results
|
Parameter |
Achieved effect |
|
Energy efficiency |
The efficiency of the electric motors was 95.45% – 95.71%. |
|
Reliability |
All electric motors passed tests under nominal load; no failures in temperature and vibration values were recorded. FAG bearings with increased service life were used. |
|
Unification |
All motors were manufactured for the same voltage of 6.3 kV and frequency of 50 Hz. |
|
Payback period / Economics |
Due to the optimization of production in the PRC, the contract cost turned out to be 48% lower than alternative offers. |
Conclusion
The project for the supply of high-voltage "EF" electric motors confirmed the ability of the "Energofront" team to solve complex engineering tasks at the intersection of aerodynamics, electromagnetic design and adaptation to extreme climatic conditions.
Successful direct-on-line starting of heterogeneous draft fans, ensuring high efficiency and significant savings in the customer's budget (reduction of the contract cost by 48%) demonstrate the company's systematic approach:
The implemented project ensured the reliable start-up of new CHP units and contributed to increasing the energy efficiency of Russian power generation.
Consolidated Case Study: Comprehensive Replacement of PE-Series Boiler Feed Pumps with Modern TDG Units at Power Generation Facilities of the Russian Federation
Comprehensive supply of pumping equipment for an energy facility — Novolenskaya TPP
Supply of DG270-140Cx10 brand feed pumps (Q=270 m3/h, 1650 m) manufactured by Shanghai Kaiquan Pump Industry (Group) Co., Ltd. (China) for the needs of PJSC RusHydro